Ratio of the work done by P, Q and R in one day is 5:3:7 respectively. They all together can complete the work in 35 days. Q and R worked on it for 20 days. In how many days P will complete the remaining work.
Let total amount work be = 35 x 15 = 525 units Amount of work done by Q and R in 20 days = 20 x 10 = 200 units Amount of work left = 525 – 200 = 325 Required time = 325/5 = 65 days
What is the key goal of the Solar Village Scheme launched by Maharashtra Chief Minister Eknath Shinde?
_________ article of the indian constitution provides for civil code for the citizens.
Which of the following statements is true about the Jan Vishwas (Amendment of Provisions) Bill, 2023 recently passed in Lok Sabha?
The ‘School Chalo’ abhiyan was recently launched in?
Sathyamangalam Tiger Reserve (STR) in __________ has been given the TX2 award after its tiger numbers doubled to 80 since 2010.
New Kwanza is the currency of which country?
The PM SVANidhi Scheme has been extended till?
All-India Consumer Price Index Number for Agricultural Labourers and Rural Labourers (Base: 1986-87=100) for the month of November, 2022 increased by __...
Which Indian financial institution’s CEO is Shanti Lal Jain?
Which integrated complex is set to host the FIH Hockey5s World Cup qualifiers before the Summer 2024 Olympic Games in Paris?