P’s 3 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 24 days then how much time Q will take to complete 75% of the work?
Ratio of efficiency of P and Q = 5:3 Let the efficiency of P and Q be 5x and 3x units per day respectively. Total work = 8x × 24 = 192x units Required time = (0.75 × 192x)/3x = 48 days