Question
20 men can complete a piece of work in 40 days. βxβ
men started the work and after 35 days 64 more men joined them so that whole work was finished in the desired time. Find the value of βxβSolution
Total work = 20 Γ 40 = 800 units According to question; 35 Γ x + 5 Γ (x + 64) = 800 Or, 35x + 5x + 320 = 800 Or, 40x = 480 Or, x = 12
What should be done in an economy to reduce the effects of recession?
Price elasticity of demand of a horizontal demand curve is called:
As a result of an increase in consumer incomes, the demand for XYZ good has decreased. Based on this information, what can we definitely say about what ...
If a 1 percent decrease in the price of a pound of squash results in a larger percentage decrease in the quantity supplied,
Which of the following methods is used to control inflation in India?
Which of the following occupations are included under secondary sector as per the national income accounts?
1. Manufacturing
2. Constructi...
Coefficient of elasticity of demand is negative. It means:
Which of the following will have the largest value while calculating national income?
Which of the following statement best describe the role of a “deflator”?
Which one of the following transactions will be considered as a transfer payment?