Question
Ganga, Yamuna &Saraswati can complete a piece of
work in 30, 40 & 60 days respectively. All 3 of them started working together and after 4 days, Ganga quits. Yamuna left 12 days before the completion of the work. In how many days the work was completed?Solution
Let total work = LCM (30, 40 & 60) = 120 units Ganga's 1 day work = 120/30 = 4 units Yamuna's 1 day work = 120/40 = 3 units Saraswati'1 day work = 120/60 = 2 units (Ganga+Yamuna+Saraswati)'s 1 day work = 4+3+2 = 9 units So work done by all in 4 days = 9 `xx` 4 = 36 days, Now Ganga Left. Now for next few days, Yamuna & Saraswati worked together & then Yamuna left 12 days before the completion , it means Saraswati alone works in last 12 days. So Saraswati's work done in 12 days = 12`xx` 2 = 24 So work done in first 4 days & in last 12 days = 36+24 = 60 units Remaining work is done by (Yamuna+ Saraswati) in = 60/(3+2) = 60/5 = 12 days So total days to complete the work = 4+12+12 = 28 days
State true or false
A ping of death attack involves sending a malformed packet to a targeted machine, resulting in deleterious behavior such ...
In pandas, what does df.groupby('A').agg({'B': 'sum', 'C': 'mean'}) return?
Which of these is a distributional representation for words?
Which is best fit for blank space 16?
What is the primary purpose of the fork() system call in Unix-based operating systems?
The ability of the device to give identical output when repeat measurement are made with the same input is defined as________
Which of the following statements best describes a mesh topology in network design?
In a nodal analysis a circuit with 10 nodes will have _______ unknown voltage and _______equation.Â
Which of these is an application of AI in healthcare?
Which of the following conditions is not one of the four necessary conditions for a deadlock to occur?