Question
Q can complete a project in βx β hours , R needs
β0.7xβ hours to do half of The same project. R and S jointly can complete the same project in 1/3 of time taken by Q to complete the work alone. Q takes 90 hours more to complete alone as compared to time taken by all three jointly to complete the work. Find the time taken by S to complete 80% of the project alone?ΒSolution
Let time taken by R to finish work is β x hr, By Q is = 1.4x hr Therefore, R+S = (1.4x/3)hr So, by S alone work = [1/3/1.4x) β 1/x ] = 7x/8 hr Entire time taken by all together = (1.4x - 90)hr Therefore, 1/x + 1/1.4x + 8/7x = 1/1.4x-90 1.4x +1+1.6x/1.4x = 1/1.4x -90 5.6x -360 = 1.4x x = 600/7 Hence, time taken by S alone to complete 80% = 7/8 x 600/7 x 0.8 = 60 hrs
Six persons N, O, P, Q, R and S sit in a straight line facing north but not necessarily in the same order. Distance between each adjacent person is equa...
Who sits third to the right of E?
Who among the following person likes Guava in the row arrangement?
Eight friends, R, S, T, U, V, W, X and Y are sitting in a line facing north. V is sitting at one of the corners. S is sitting between Y and T. X is sitt...
Which of the following is correct?
Who sits immediate left of D?
Which of the following person works in company O?
Which of the following laptop does C use?
Who among the following person sits fourth to the left of P?
How many persons are older than S?Β Β Β Β