A and B can do a work in 24 days and 32 days, respectively. If A works on it for ‘x’ days and B works on it for ‘x – 1’ days, then one-third of the work gets completed. Find the value of ‘x’.
Let the total work = 96 units {LCM of 24 and 32} Efficiency of A = 96/24 = 4 units/day Efficiency of B = 96/32 = 3 units/day According to the question; 4 × (x) + 3 × (x – 1) = (1/3) × 96 Or, 4x + 3x – 3 = 32 Or, 7x = 35 Or, x = 35/7 = 5
Kalakkad-Mundanthurai Tiger Reserve lies in which one of the following regions?
Which of the following launched the “NIPUN- Bharat” initiative?
Taiwanese contract manufacturer Foxconn plans to invest Rs 4,000 crore in a new electronics manufacturing facility in which Indian state?
Which country passed its first-ever legislation to combat violence against women, including practices like forced marriage and female genital mutilation?
Which of the following substances is referred to as White Vitriol?
Which district registered the maximum number of home stays for the financial year 2022-23 as of Dec 2022?
World Bank has recently (in June 2023) launched its first road safety project in which South Asian Country?
Consider the following statements about Central Bureau of Investigation (CBI):
1. It was set up by a resolution of 1963 of the Ministry of La...
What major decision did the Uttarakhand government make regarding Patanjali Ayurved's products?
When was the National Council of Educational Research and Training (NCERT) established?