Question
Sonal completed 30% of work alone and left the remaining
work for Vinod who completed it in 28 days. If the total work got completed in 40 days, then find the time taken by Sonal and Vinod together to complete the whole work.Solution
Total time taken by Vinod alone to complete the work = (28/7) x 10 = 40 days Total time taken by Sonal alone to complete the work = (12/3) x 10 = 40 days Let total work be 40 units. Hence, the Required time will be = 40/2 = 20 days
Which one enacts the establishment of an Inter-State Council to facilitate the seamless conduct of affairs between the Union and states and the resoluti...
In which year was the Lakdawala Committee on Poverty established?
Which of the following Vedas is concerned with the origin of Indian Medicine?
Sulochana Chavan passed away at the age of 92 years she was famous?
When was the Reserve Bank of India nationalized?
What was the name of the women's regiment formed by Subhash Chandra Bose in 1943?
Pullampara is now the first fully digital literate panchayat in India. It is in which state?
Price earnings (PE) ratio shows how much an investor is willing to pay for each rupee of the earnings given the actual market price
किस भारतीय मूल की महिला ने अंतरिक्ष में सर्वाधिक समय तक रह...
Which of the following UT has been declared as the most densest populated Union Territory in the country?