Question
Anmol can do a piece of work in 30 days, Bineet can
complete double the work in 90 days and Chintu can do the work in 60 days. If all of them jointly gets Rs.2600. then, what will be the money earned by Anmol.Solution
ATQ, we can say that Time taken by Anmol = 30 days Time taken by Bineet = 45 days (Since, Bineet is working double in 90 days) Time taken by Chintu = 60 days Let the total work be done by them is 180 units. Anmol’s one day work = (180/30) = 6 units Bineet’s one day work = (180/45) = 4 units Chintu’s one day work =(180/60) = 3 units Hence, the Amount earned by Anmol is = (2600/13) x 6 = Rs.1200
What significant achievement did Jiya Rai accomplish in July 2024? Â
What significant milestone did Rohit Sharma achieve in T20 cricket?
With reference to DINKAR herbicide launched by Dhanuka Agritech, consider the following statements:
1. DINKAR has been developed in collaboration...
What is the primary objective of the 'One India-One Ticket' initiative?
With what percentage of votes did Paul Kagame win his fourth term as Rwandan President?
With reference to the outcomes of Prime Minister’s recent visits to Namibia and Brazil, consider the following pairs:
Which Indian state recorded rural inflation of 4.10% in July 2024?
What is the base year for the Quick Estimates of IIP (Index of Industrial Production)?
The traffic came to a standstill after the heavy downpour of rain.
The National Informatics Centre (NIC) and Spices Board of India recently signed an MoU to develop AI tools for detecting and classifying large cardamom ...