Arjun and Bheem can do a piece of work in 8 and 10 days
respectively. If they started the work together and worked on it for 3 days, then find the time taken by B alone to complete the remaining work.Solution
ATQ, Let we can assume that the total work be 40 units Arjun ’s one-day work will be then= 5 units Bheem’s one-day work = 4 units Then, Work done by Arjun and Bheem together in 3 days = 9 x 3 = 27 days Therefore, the rest work will be = 40 – 27 = 13 units Hence, the required number of days will be = 13/4 = 3.25 days
Book entitled “Plowman’s Folly: A Second Look” was written by _____
_______ is known as biological reduction
H+ and Al3+ ions present in non-exchangeable form with organic matter and silicate clays and aluminum hydroxyl ions account for
What is the symptom of calcium deficiency in crops?
Economic Life span of coconut in years for coconut palm?
Which of the following is not a method of calculating National Income?
Sex-influenced traits are autosomal qualities that are impacted by sex. An example of sex influenced traits is
Glufosinate inhibits the enzyme
---------------is a method where new genes are introduced into an organism's chromosomes to change its genetic makeup?
Nobilization of Sugarcane in India was done by