Question
A, B and C can complete a work in 10 days, 20 days and
30 days respectively. A and C started the work together and they both work for 6 days. If the remaining work is completed by B and D in 3 days, then find the number of days taken by D to complete (1/5)th of the same work.Solution
Let the total work (LCM of 10, 20 and 30) = 60 units Efficiency of A = 60/10 = 6 units/day Efficiency of B = 60/20 = 3 units/day Efficiency of C = 60/30 = 2 units/day Work done by A and C together in 6 days = 6 × (6 + 2) = 48 units Remaining work = 60 – 48 = 12 units Efficiency of D = (12/3) – 3 = 1 unit/day Number of days taken by D to complete (1/5)th of the same work = (60/5)/1 = 12 days
A number, when divided by 64, leaves a remainder of 47. What will be the remainder when it is divided by 16?
- When 65% of a number is added back to the number, the increase is found to be 39. What is the final value obtained?
What is the largest three-digit number that leaves a remainder of 5 when divided by both 11 and 13? Call this number a. Additiona...
- Consider the given question and decide which of the following statements is sufficient to answer the question.
‘N’ is any natural number. When it wi... - Find the number of possible digits 'm' such that the number 3816mn is divisible by 15.
Find the fourth proportional of 12, 24, and 30.
Find the sum of all natural numbers from 1 to 300 which are divisible by 7.
Find the difference between minimum and maximum value of 'c' such that '5c4632' is always divisible by 3.
- When a number is divided by 23, the remainder obtained is 17. What will be the remainder when three times the same number is divided by 23?
When the digits of a two-digit number are interchanged, the new number becomes 24 more than 180% of the original number. If the sum of the digits is 6, ...