A certain Sales target was assigned to a team of men to
complete in 18 days. But 8 men did not turn up for the target and the rest men complete the sales target in 30 days. What was the original number of men in the team?
A19Correct AnswerIncorrect Answer
B12Correct AnswerIncorrect Answer
C20Correct AnswerIncorrect Answer
D35Correct AnswerIncorrect Answer
Enone of theseCorrect AnswerIncorrect Answer
Solution
ATQ, we can say that Let the original no. of men in the team be taken as = ‘x’ then, 18x = 30(x - 8) 12x = 240 x = 20 men