ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    Amit can do certain work alone in 'w' days. Arjit can do

    the same work alone in (w + 12) days.Gaurav started working and did (1/2) the work at the efficiency of Amit and rest work at efficiency of Arjit, and finished the work in 24 days. Then, find the value of (w2 + 5w -40)
    A 450 Correct Answer Incorrect Answer
    B 650 Correct Answer Incorrect Answer
    C 370 Correct Answer Incorrect Answer
    D 374 Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    ATQ, we can say that Since 'Gaurav' completed (1/2) of the work with (1/2) the efficiency of 'Amit'.┬а So, time taken by him to complete (1/2) of the work = (w/2) days Similarly, time taken by 'Gaurav' to complete other (1/2) of the work =┬а [(w + 12)/2] days So, (w/2) + {(w + 12)/2} = 24 Or, w + 6 = 24 Or, w = 18 So, w2 + 5w - 40 = 324 + 90 - 40 =┬а 324 + 50 = 374

    Practice Next
    More Time and work Questions
    ask-question