Question
Aman, Arun and Abraham can complete a work in 12, 20 and
24 days respectively. They all start working together. Aman left the work 1 day before its completion, Arun 3 days before, Abraham 4 days before. In how many days the work is finished?Solution
Note: Here Aman leaves the work 1 day before the completion of the work, Arun 3 days before and Abraham 4 days before. If the work of the left days of these three is added, then together they can start and finish the work. Â Â Â Â Â Â Â Â Â Â Â Total work = 120+10+18+120 =168
Which Schedule of the Constitution of India prescribe Forms of Oaths and Affirmations?
Who bears the burden of proof in a legal proceeding when establishing the existence of facts?
Under the Indian Partnership Act, 1932, Section 13, partners are entitled to which of the following by default?
V conceals information about a planned cheating offence (punishable with 7 years imprisonment). Compare his punishment if: (i) the cheating is committed...
Which of the following best represents the provision under BNS regarding right of private defence?
Under Section 53 of the BNSS, 2023, regarding the medical examination of an arrested female person, which of the following statements is correct?
Which of the following is a wrong combination of number of arbitrators in an arbitral tribunal?
The accused in the instant case was charged for killing a person by driving over him. A witness saw the vehicle at a high speed, but did not see the ac...
The Board shall, ________ of the receipt of a reference from the Adjudicating Authority  for the recommendation of an insolvency professional who may...
Consider the following statements regarding Section 43A (Data Protection) of the IT Act, 2000:
Statement 1: A body corporate has a statutory d...