Question

    A and B can finish a piece of work in 20 days and 30 days respectively. Both work on alternate days. In how many days will the work be completed when A starts the work?

    A 12 Days Correct Answer Incorrect Answer
    B 24 Days Correct Answer Incorrect Answer
    C 18 Days Correct Answer Incorrect Answer
    D 36 Days Correct Answer Incorrect Answer

    Solution

    Both work alternately on alternate days. A starts first. Thus, 5 units can be worked in 2 days, so time taken to work 60 units = 60/5 =12 Days.

    Practice Next
    ×
    ×