Question
Anupam can do a piece of work in 36 days and Rajveer can
do it in 15 days. Diksha can do the same work in (17/18) times the number of days required by both Anupam and Rajveer together. Initially Anupam and Rajveer worked together for 8 days and then both left. Diksha completed the rest of the work. For how many days did Diksha work?Solution
ATQ, we can say that the Part of the work done by Anupam and Rajveer in one day is = [1/36 + 1/15] = 17/180 Number of days required by Diksha to complete the entire work alone = (17/18) × (180/17) = 10 days. 8 × (17/180) = (34/45) work completed by Anupam and Rajveer. Leftover work for Diksha is = (11/45)th work. Then number of days for which Diksha will worked is = [(11/45) × (10/1)] = (22/9) days
Which organization does Pradip Kumar Das currently lead as the CMD, earning him the distinguished "CMD of the Year" award in the Mini-Ratna category at ...
Which two Indian institutes signed an MoU in May 2025 to enhance ground-based space situational awareness?
As a step to grow business HDFC bank will begin to provide premium banking services, named as _______ to various customer groups, such as farmers, micro...
Which state in India launched the country’s first supercapacitor manufacturing facility?
How many fake mobile connections have been disconnected using the Sanchar Saathi platform as of 2025?
What percentage of deposits were held by individuals as of September 2024, according to the RBI Quarterly BSR-2 report?
How much increase has been made by the Union Government domestic natural gas prices for October 2023?
Which country has agreed to transfer sovereignty of the Chagos Islands to Mauritius?
 In which state Wangala Festival is celebrated?
SEBI introduced the Mutual Funds Lite (MF Lite) framework to offer more flexibility in passive schemes. What is the minimum investment required for inve...