ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    'B' is 20% more efficient than 'A.' 'A' began working on

    a task alone and continued for 8 days, after which 'B' took over and completed the remaining work alone in 5 days. Now, In how many days 'A' would require to complete the entire task if they worked alone.
    A 12 days Correct Answer Incorrect Answer
    B 14 days Correct Answer Incorrect Answer
    C 24 days Correct Answer Incorrect Answer
    D 11 days Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    ATQ, Let the efficiency of тАШAтАЩ = тАШ10yтАЩ units/day Then, efficiency of тАШBтАЩ = 10y ├Ч 1.2 = тАШ12yтАЩ units/day So, total work = (10y ├Ч 8) + (12y ├Ч 5) = тАШ140yтАЩ units So, time taken by тАШAтАЩ to complete the whole work alone = (140y/10y) = 14 days

    Practice Next
    More Time and work Questions
    ask-question