Question

    A team of 32 men and 28 women can complete a task in 60 days. When an additional eight men join the team, they are able to finish (4/5) of the same task in 40 days. What is the amount of time needed for 84 women to complete 200% of the same task?

    A 120 days Correct Answer Incorrect Answer
    B 150 days Correct Answer Incorrect Answer
    C 100 days Correct Answer Incorrect Answer
    D 200 days Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    ATQ, Let the efficiency of a man and a women be 'a' and 'b'  units/day respectively Then, [(32a + 28b) × 60]/1 = [(40a + 28b) × 40]/(4/5) 192a + 168b = 200a + 140b (a/b) = (7/2) Total work = [((32 × 7) + (28 × 2)) × 60] = 16800 units hence required days = [(2 × 16800) /(84×2)]  = 200 days