Question

    A alone can finish the work in 10days and B alone can finish the same work in 15 days. All A, B and C together take 5 days to finish the work. Find the time in which the same work can be completed in a sequence such that A starts first then B and then C.

    A 15 Correct Answer Incorrect Answer
    B 12 Correct Answer Incorrect Answer
    C 9 Correct Answer Incorrect Answer
    D 18 Correct Answer Incorrect Answer
    E None of the above Correct Answer Incorrect Answer

    Solution

    Total amount of work = LCM(10,15,5) = 30 Efficiency of A: 30/10 = 3units/day Efficiency of B: 30/15 = 2units/day Efficiency of A+B+C = 5 units/day => Efficiency of C=6-3-2=1 unit/day Work done by A+B+C together in 3 days = (3+2+1)×1 = 6 unit Total number of days required to finish the work: 30/6 => 5×3 = 15 days

    Practice Next

    Relevant for Exams:

    ×
    ×