Question
'R' takes 20 days to complete a task, and 'A' takes 30
days to do the same task. To finish the job in just 6 days, what percentage increase in their respective efficiencies is required by 'R' and 'A'?Solution
We can say that Let the total work = 60 units (L.C.M of 20 & 30) Efficiency of 'R' = 60/20 = 3 units /day Efficiency of 'A' = 60/30 = 2 units/day Their combined efficiency = 2 + 3 = 5 units/day To complete the work in 6 days, there combined efficiency should be 60/6 = 10 units/day Required percentage increase = {(10 – 5) × 100}/5 = 100%
On purchase of old furniture, the amount of ₹1,000 spent on its repair should be debited to:
What is the main purpose of the Central KYC Records Registry (CKYCR) in India?
Which of the below import duties would be imposed?
State which statement is correct:
What is the primary role of the Central KYC Records Registry (CKYCR)?Â
Which Ind AS deals with Revenue from Contracts with Customers?
Accounts relating to income, revenue, gain expenses, and losses are termed as:
What is the maximum deduction allowed under Section 80U of the Income Tax Act, 1961, for an individual with a severe disability?
According to RBI’s circular on External Benchmark Based Lending, which of the following is not listed as an eligible external benchmark?
A consignor sends goods costing ₹2,00,000 to consignee at invoice price of 125% of cost. 1/10th goods are lost in transit (abnormal). Consignee sells ...