Question
'Preeti' can complete a piece of work in 70 days, while
'Bhanumati' can complete it in 90 days. They both started the work together, but 'Preeti' left after 23 days. 'Bhanumati,' with the assistance of 'Chirag,' completed the remaining work in 21(5/6) days. Calculate the time required for 'Chirag' to complete the entire work on his own.Solution
ATQ, Let total amount of work = 630 units (LCM of 90 and 70) Efficiency of ‘Preeti’ = 630/70 = 9 units per day Efficiency of ‘Bhanumati’ = 630/90 = 7 units per day Amount of work completed by ‘Preeti’ and ‘Bhanumati’ together in 23 days = 16 × 23 = 368 units Remaining work = 630 – 368 = 262 units Efficiency of ‘Bhanumati’ and ‘Chirag’ together = 262/(131/6) = 12 units per days So, efficiency of ‘Chirag’ = 12 – 7 = 5 units per day Hence required time = 630/5 = 126 days
In the word ‘MEASUREMENT’ all consonants are written as their preceding letter and all vowels are written as their following letters. Now al...
Select the figure from the options that can replace the question mark (?) and complete the given pattern.
In a certain code language, ‘athlete had taken’ is coded as ‘ht, ku, wh’, ‘treatment had recovered’ is coded as ‘ms, kr, ht’, ‘recover...
In the given question, three of them are alike and one is different. Identify the odd one out
What is the code for ‘turned into’?
Select the option that is related to the fifth letter-cluster in the same way as the second letter-cluster is related to the first letter cluster and th...
To whom M is married?
Read the directions carefully and answer the following questions.
Samson, Gill, Bumrah, Pant, Shami, Rohit and Siraj are of different weights. ...
Select the option in which the numbers are related in the same way as are the numbers of the following sets.
 (52, 13, 8)
(96, 16, 12) �...
Select the correct combination of mathematical signs to sequentially replace the * signs and balance the given equation.
88 * 44 * 22 * 66 * 99 * 251