Question
"A certain sales target can be completed by a team of both men and womens in 60 days. If you replace eight womens with eight men, the same target can be accomplished in 75 days. If you further substitute five womens with five men in the original team,determine the time it takes for them to complete 70% of the sales target."
More Time and work Questions
- 'A' alone can do some work in 20 days. 'B' is 60% more efficient than 'A'. 'A' worked alone for 12 days and left. How much time (in days) does 'B' need to ...
- Sneha and Meena can complete a project in 24 days and 60 days respectively. Sneha began working first. After how many days should Meena step in so that the...
- 'K' and 'L' together can complete a work in 24 days. They started working together but after 16 days, 'L' left and remaining work was completed by 'K' alon...
- ‘A’ and ‘B’ can do a piece of work in 10 days and 15 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then find the time ...
- Rahul can complete a work in 12 days and Ayush in 15 days. If they work together for 3 days, then the fraction of work that will be left is:
- Some Category of workers can complete a decided project in 20 days. However, due to some unpredicted situation, 5 workers were absent. That’s why, the proj...
- Person A can complete a work in 90 minutes while Person B takes 54 minutes to complete the same work. How much time will both take together to complete the...
- ‘A’ can finish a project in 40 days, whereas ‘B’ finishes 50% of the project in 12 days less than ‘A’. How many days will it take both ‘A’ and ‘B’ to compl...
- Time taken by A and B together to complete a work is 1 day less than the time taken by B alone to complete the same work. With his half efficiency B can co...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)