Question
A and B can complete a job together in 30 days; B and C can complete the same job together in 25 days, while C and A can complete the same job together in 10 days. In how many days will A, B, and C be able to complete the same job alongside D, who is only 50% as efficient as C?
More Time and work Questions
- Two typists of different speeds can complete a typing job together in 6 minutes. If the 1st typist types alone for 4 minutes and then the 2nd typist types ...
- ‘R’ and ‘S’ can do a piece of work in 20 days and 30 days, respectively. ‘R’ started working alone and was replaced by ‘S’ after 10 days. In how many days ...
- 15 men working 9 hours daily can finish a task in 36 days, while 18 women working 6 hours a day complete the same task in 72 days. How many days will 6 men...
- Ratio of the work done by P, Q and R in one day is 7:3:8 respectively. They all together can complete the work in 42 days. Q and R worked on it for 21 days...
- Time taken by 'A' to complete a work is 12 days less than that taken by 'B' to complete the same work. On working together, they can complete the work in 8...
- Eight men and five boys together earn ₹3,240 in 6 days. Meanwhile, three men and two boys working together take 12 days to earn ₹2,484. How many days will ...
- Virat can do a piece of work in 28 days and Sachin can do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will...
- 4 men earn Rs. 960 altogether for working 8 days. If a woman earns Rs. 4 more than each man per day, what will be the total earnings of 10 women in 5 days?
- 30 workers are laying a 6 km railway track. After 18 days, they finish 3/5 of the total work. To speed it up, 10 more workers are added. How many days will...
- A and B together can complete a piece of work in 8 days. B and C together can also complete it in 8 days, while A and C together can complete it in 6 days....
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
Total 2(A+B+C) = 5+6+15+=26 A+B+C =13 C = 13-5 =8 D= 8×50/100=4 NOW A+B+C+D = 13+4=17 SO total days = 150/17 =150/17