Question
A and B can complete a job together in 30 days; B and C
can complete the same job together in 25 days, while C and A can complete the same job together in 10 days. In how many days will A, B, and C be able to complete the same job alongside D, who is only 50% as efficient as C?Solution
A+B= 30 B+C=25 C+A=10days LCM of 30, 25, and 10 = 150
Total 2(A+B+C) = 5+6+15+=26 A+B+C =13 C = 13-5 =8 D= 8×50/100=4 NOW A+B+C+D = 13+4=17 SO total days = 150/17 =150/17
Division of Agricultural Meteorology at Pune was established in:
Two satellites are orbiting Earth at different altitudes. Satellite A is closer than Satellite B. Which of the following is correct regarding their spe...
Two charges +4μC and +9μC are separated by 60 cm. Where should a third charge be placed so that it experiences zero net force? (from +4μC charge)
Which element has the highest electron affinity?
The temperature which has the same reading on both Fahrenheit and Celsius scales is –
The electrical conductivity of a semiconductor increases with rise in temperature because:
A body is thrown vertically upward. At the highest point of its motion, which of the following is true?
A man cannot see clearly beyond 10 meters. The disease he suffers from :
Which of the following two chemical reactions are involved in the corrosion of the iron metal?
The 'Red Data Book' published by IUCN contains information on: