Question
Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion of the work. Then the total work is completed in how many days?
More Time and work Questions
- A buffalo alone can plough field ‘A’ in 10 days. A Bull alone can plough the field ‘A’ in 16 days. Find the number of days taken by 1 bulls and 3 buffalo t...
- A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- The efficiency of C is 20% more than the efficiency of D. D alone can complete a piece of work in (y-2) days. The time taken by C alone to complete the wor...
- 40 men or 50 women can build a wall in 30 days. If 40 men and 50 women work together, how many days will they take to complete 60% of the work?
- Suppose Y individuals can complete a task in (Y - 28) days, and (Y + 12) individuals can finish the same task in (Y - 32) days, what is the number of days ...
- 105 people could complete a work in 36 days. But after they worked together for 7 days their employer wanted the work should be completed in a total of 28 ...
- A person can complete a work in 15 days, and another person can complete the same work in 20 days. They work together for 5 days, and then the first person...
- The time taken by ‘A’ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time required by...
- 25 men can complete a piece of work in 13 days. One man starts the work and after every day one more man joins the work and this continues till the work is...
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)