Question

    V and N, working individually, can complete a task in (w – 2) days and (w + 4) days, respectively. N initiated the task alone and was later joined by V after 10 days. Together, they completed the remaining work in the next 6 days. Determine the value of 'w.'

    A 5 Correct Answer Incorrect Answer
    B 12 Correct Answer Incorrect Answer
    C 20 Correct Answer Incorrect Answer
    D 25 Correct Answer Incorrect Answer
    E 15 Correct Answer Incorrect Answer

    Solution

    ATQ, Let total work = {(w – 2)(w + 4)} units Efficiency of 'V' = {(w – 2)(w + 4)}/(w – 2) = (w + 4) units/day Efficiency of 'N' = {(w – 2)(w + 4)}/(w + 4) = (w – 2) units/day ATQ; 10 × (w – 2) + 6 × (w + 4 + w – 2) = (w + 4)(w – 2) Or, w2 = 20 w Or, w = 20

    Practice Next
    ×
    ×