Question
A can complete 25% of work in five days. And this takes
four days more than B to complete the whole work. They started the work together but after X days A left and C was 50% as efficient as a joined B and completed the whole work with him. If the total work got completed in 2X days, then find the value of X.Solution
Time taken by A to complete the whole work alone = 20 days. time taken by B To complete the whole work alone = 20-4 = 16 days Let total work = 80 unit (LCM of 20 and 16) Efficiency of A= 80/20 = 4 units/day Efficiency of B = 80/ 16 = 5 Units/day. Efficiency of C = 0.5*4 =Β 2 units/ day Also B&C together worked for= X days. (4+5)*x+(5+2)*x = 80 16x=80 X=5 Therefore efficiency of D,= (X + 11)= 16 units / day Required. Time taken. = 80/16 = 5 days
- What will come in place of the question mark (?) in the following series?
1, 2, 5, 16, 65, ? 7 12 33 ? 635 3804
...In each of the following number series, one term is missing. Find the missing term.
1, 4, 15, 64, ?, 1956
What will come in place of the question mark (?) in the following series?
6, 13, 29, 63, ?, 259
What will come in place of the question mark (?) in the following series?
111, 109, 115, ?, 211, -509
362 452 550 656 770 892 ?
...What will come in place of the question mark (?) in the following series?
25, 41, 73, ?, 185, 265
Find the missing number in the given number series.
2, 7, 19, 62, ?, 1270Β
What value should come in place of (?) in the given number series.
500, 499, 491, 464, ?, 275
114, 146, 210, 306, 434, ?