A and B working together completed a job in 40/9 days. If A had worked twice as efficiently as she did and B had worked 1/3 of his actual efficiency, then the work would have been completed in 60 /17 days. Find the time A would take to complete the work alone.
More Time and work Questions
- 'B' alone can complete a work in 16 days while 'A' and 'B' together can complete the same work in 8 days. 'A' alone started the work and left after 4 days ...
- A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job an...
- 18 men, working 8 hours a day, can complete a task in 21 days. If a woman is 33(1/3)% less efficient than a man, how much time will it take for 24 women, w...
- Aman and Bheema together can finish 50% of a task in 12 days, while Chinky alone can finish 30% of the same task in 12 days. Determine the time required fo...
- X can do a piece of work in 20 days. He worked at it for 4 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
- Amit is 66(2/3)% more efficient than Vivek who can do the same work in 25% more time than Sameer. If Amit and Sameer together can complete 70% of work in 1...
- A and B together do a job in 12 days. A alone does it in 20 days. How many days for B alone?
- Pawan completes in two days the same amount of work that Qureshi completes in four days. Pawan alone can finish the entire task in 15 days. How many days w...
- 105 people could complete a work in 36 days. But after they worked together for 7 days their employer wanted the work should be completed in a total of 28 ...
- Karan is capable of doing 50% of a job in 25 days, while Meera does 25% of it in 20 days. Karan works for 20 days and then leaves. How many days will Meera...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
20A=25B A/B=25/20 A/B=5/4 A: B=5:4 ATQ- Total work= (40/9) ×9 =40 Total work completed by A = 40/5=8 days