Question
Raj, Sanjay and Vaibhav can separately finish a work in
20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by Sanjay and Vaibhav and alternates days starting with Sanjay.Solution
RajSanjayVaibhav 203040 120 643 Working type – (Raj+ Sanjay) (Raj +Vaibhav) Working in first 2 days =10+9=19unit Working in 2×6=12 days =19×6=114unit 13days-6/10=3/5 Total time =12+3/5=63/5days
Which of the is/are correct for the determination of PVTGs in India?
Which of the following institutions is in last mile financer under Aajeevika Microfinance Yojana (Livelihood Microfinance Scheme)?
As on February 2022, how many countries have participated in the Human Capital Project?
Which of the following is NOT a key focus area of the Smart Cities Mission?
Polymorphism in fungi was first observed by:
Which of the following options is not one of the aims of National Nutrition Mission?
The Pradhan Mantri Vaya Vandana Yojana (PMVVY) recently completed six years. The PMVVY launched in 2017 by which ministry?
Which of the following is not one of the advantages of PM KISAN scheme?
Which of the following is not the parameters of niti aayog’saspirational district index?
What is the coverage period for the Pradhan Mantri Jeevan Jyoti Bima Yojana?