Question
A civil contractor planned to build an over bridge of 3
km distance in 600 days. For this purpose, he employed 90 workers. After 200 days of work, it was observed that only 0.5 km of the bridge was completed. What is the number of extra workers required to complete the work on timeSolution
W1=1/6, W2=5/6 (M1 × D1× H1)/W1= (M2 × D2 × H2)/W2 (90 × 200)/1/6 = (M2 × 400)/5/6 M2 = 225 Þ Extra people = 225 – 90 = 135.
For a large infrastructure project, which of the following is typically the MOST expensive source of finance?
The main objective of cost accounting is _______.
A pharma company spends ₹50 crore on early-stage drug molecule research (feasibility not established). Later spends ₹30 crore proving commercial via...
Which country has officially joined the New Development Bank (NDB) in May 2025?
The rate of TDS for Rent of Land and Building, Land appurtenant to a building is:
A company has debt of ₹50 lakh at 10% interest, equity of ₹1 crore with cost of equity 15%, and tax rate 30%. Calculate the WACC (weighted by market...
The return forgone for the undertaking an investment is known as?
Who is the designated authority to receive information under the reporting requirements of the PML (Maintenance of Records) Rules, 2005?
The government’s GST Sahay app is designed to help MSMEs with:
What is the journal entry for charging Depreciation under Cost Method?