Raju, Shubham, and Mohan can work for 15 days, 20 days and 25 days respectively. In how many days will the work be finished if they do it on alternate days?
RajSubhamMohan 152025 LCM-300 201512 Working type- Raj, Subham, Mohan, Raj, Shubham, Mohan…. Working in first 3days =20+15+12 =47units 3×6days =47×6=282units 18days =282units 19days =18/20=9/10days Total days = 18+9/10=189/10days
Three of the following four number-pairs are alike in a certain way and one is different. Find the odd one out.
Arrange the following in the English alphabetical order:
(i) Palatine
(ii) Palatalize
...The following series is based on the English alphabets. Which one of the following will come in place of the question mark in the given alphabetical ser...
Select the correct option that indicates the arrangement of the given words in the order in which they appear in an English dictionary
1. Petitio...
Select the term that will come next in the following series.
14, 16, 20, 26, 34, 44, 56, 70, 86, ?
A series is given, with one term missing. Choose the correct alternative from the given ones that will complete the series.
W, V, T, Q, M ?
In a certain code language, '+' represents '×', '-' represents '+', '×' represents '÷' and '÷' represents '-'. What is the answer to the following q...
Three of the following four words are alike in a certain way and one is different. Find the odd one out.
Six person U, V, W, X, Y and Z are sitting around a circular table facing each other (not necessarily in the same order). X is on the immediate right of...
Select the correct option that indicates the arrangement of the given words in the order in which they appear in an English dictionary.
1. Dermat...