Question
A, B, C can do a piece of work in 11 days, 20 days, and
22 days respectively. If B works daily and is supported by A and C on alternate days beginning with A, then in how many days will the work be finished?Solution
ABC 112022 220 201110 working fashion = (A +B, C + B) 2 days = 31 + 21 = 52 units 8 days = 208 units Remaining work =220-208=12unit 9 days = 12/31 => 220units Total time =8+(12/31) days=8 +(12/31 days
 Consider the following statement about Global Hunger Index report 2023:
1. India ranks 111th out of the 125 countries
2. According to th...
Where has India’s first floating elementary school been inaugurated?
The Karewa formations are found in the ____________.
Match List-I with List-ll and select the right code -
What was the reason for the gathering of people at Jallianwala Bagh to protest and oppose?
_______ was the oldest newspaper in India?Â
What was India's rank in the Asia-Pacific Personalised Health Index released by the Economist Intelligence Unit in January 2021?
In a business firm, assets of the business are valued on the basis of their intrinsic value rather than realizable value. This accounting is based on
What is the name of the optimized Learning Management Information System designed for healthcare workers and administrators to acquire globally relevant...
Amnesty International has its headquarters at-