A does 55% of some work in 12 days. Later, with B’s help, she completes the remaining work in 4 days. In how many days can Be B complete the entire work alone?
Let total work = 120 units A does 45% of the work=120×45/100=36 Since A does 45% of the work (i.e. 36 units) in 12 days, A = 36/12 = 3 units per day Work left = 120 − 36 = 84 units Let B do x units of work per day. B and A finish the pending work in 4 days. ∴ 4(x + 3) = 84 ∴ 4x = 84 − 12 = 72 i.e. x = 18 units ∴ Time taken by B to complete the work = 120/18 = 6+2/3 days
A reaper is used for
Given below are two statements, one is labelled as Assertion A and the other is labelled as Reason R
Assertion A: Sulphuric acid can be used to a...
Kisan Credit Card scheme was launched in which year?
Which of the following fruit ripe even after removing from the plant/tree?
Which one of the following climatic region is predominant in acid soils?
Phytoplankton
During 2020-21 NAFED did what under Price Support Scheme?
Mutations are.................?
Which of the following is not considered as green house gas?
Which of the following nutrient plays key role in sugar synthesis in Sugarcane?