A does 55% of some work in 12 days. Later, with B’s help, she completes the remaining work in 4 days. In how many days can Be B complete the entire work alone?
Let total work = 120 units A does 45% of the work=120×45/100=36 Since A does 45% of the work (i.e. 36 units) in 12 days, A = 36/12 = 3 units per day Work left = 120 − 36 = 84 units Let B do x units of work per day. B and A finish the pending work in 4 days. ∴ 4(x + 3) = 84 ∴ 4x = 84 − 12 = 72 i.e. x = 18 units ∴ Time taken by B to complete the work = 120/18 = 6+2/3 days
1)placit
2)imersed
3)imperative
4)ambiguos
In each group, one word is correctly spelt. Find the correct word.
The body of priests not only said any communal (A) tension would have an adverse (B) impact on the economy of the temple town but also sought (C) ...
Directions: In each question below, four words printed in bold type are given. These are numbered (A), (B), (C) and (D). One these words printed in bo...
In each group, one word is correctly spelt. Find the correct word.
In each group, one word is correctly spelt. Find the correct word.
In each of the questions below, a sentence is given with four words highlighted in bold in the sentence. Among these bold words, one may be wrongly spe...
Select the word with the correct spelling.
Choose the correctly spelt word?
Choose the word with correct spelling.