Question

    A’ and ‘B’ alone can do a certain work in 20 days

    and 30 days, respectively. Both started the work together but after ‘x’ days ‘A’ left the work and the rest work was completed by B alone in ‘2x’ days. Find the total time taken to complete the whole work in this way.
    A 110/3days Correct Answer Incorrect Answer
    B 120/7days Correct Answer Incorrect Answer
    C 121/7days Correct Answer Incorrect Answer
    D 154/3days Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    Total work = 60 units (LCM of 20 and 30) Efficiency of ‘A’ = 60/20 = 3 units/day Efficiency of ‘B’ = 60/30 = 2 units/day According to the question, ‘A’ worked for ‘x’ days and ‘B’ worked for ‘2x days. Therefore, 3x + 2 × 2x = 120 Or 3x + 4x = 60 Or x = 60/7days total time taken to complete the whole work = 2×60/7=120/7days

    Practice Next