Question
P is 60% more efficient than Q. P takes 30 more days to
finish a work as compared to the number of days taken by P and Q together to finish the same work. Find the time taken by Q to finish the same work alone.Solution
Let efficiency of P = p and efficiency of Q = q p = 160% of q => p: q = 8: 5 Let time required by P and Q together to finish this job be “t”. (p + q) ×t = W => 13x × t = W …. (1) ATQ- p × (t + 30) = W => 8x × (t + 30) = W … (2) By solving above two equations we get t = 48 13x × 48 = 5x × T => T = 124.8 days
When it comes to time management, how do you typically approach your tasks?
How do you prefer to work on a team?
How do you approach problem-solving?
How do you deal with failure?
How do you typically handle failures or setbacks?
How likely are you to take charge in a group setting and lead others?
How do you balance your desire for achievement and success with your need for work-life balance?
How do you feel about taking risks?
Do you prefer to work alone or in a group?
When presented with a problem, how do you typically come up with a solution?