Question
Twenty laborers can complete a piece of work in 12 days.
If 20 laborers started working and after 3 more days, additional laborers joined to complete the remaining work in 6 days, determine the number of laborers who joined after 3 days of the work started.Solution
ATQ, Let the number of Laborers joined after 3 days of the work started be ‘a’. 20L × 12 = 20L × 3 + (20 + a) L × 6 240L = 60L + 120L + 6aL 60L = 6aL a = 10
Find the force exerted on a body of mass 2 kg moving with an acceleration of 3 m/s².
A machine does 600 J of work in 2 minutes. Find its power.
What is the unit of electric current?
What is the main difference between alternating current (AC) and direct current (DC)?
What was invented by 'Zacharias Janssen'?
A body is thrown vertically upward. The work done by gravity is:
Which law states that "the rate of heat loss of a body is directly proportional to the temperature difference between the body and its surroundings"?
The Pointing vector of electromagnetic waves has the same dimensions as that of:
The heat required to raise the temperature of 1 kg of water by 1°C is called:
Which of the following is not a natural polymer?