Question
Saurabh can complete a piece of work in 20 days. He
worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both of them had done the work together, the work would have been completed in how many days?Solution
Saurabh can complete a piece of work in 20 days=1 Saurabh can complete a piece of work in 1 days=1/20 After 5 days =5/20=¼ remaining work=1-¼=¾ ATQ- Anirudh ¾ =12days Anirudh can do a work =16 days so now Saurabh       Anirudh 20                16          80 4                  5 Saurabh and Anirudh had done work complete=80/5+4 =80/9 = 889days Â
A coastal area was flooded with sea water and resulted in heavy salt deposits in the nearby area. After a few days, it was observed that many plants die...
Which of the following parameters contributed to the DPI value of 445-50 for March 2024?
How many Grand Slam titles has Australian tennis player Ashleigh Barty won so far?Â
 What is the Capital Adequacy Ratio (CRAR) required for Urban Cooperative Banks (UCBs)?
Which of the following organizations is not a regulatory body?
Chinnar Wildlife Sanctuary is located in which Indian state?
Which one of the following statements is correct as per the Constitution of India?Â
The Lesser Himalaya is separated from the ‘Dun’ by the which of the following?
The 7th World Ayurveda Congress (WAC) was held from December 2 to 4, 2016 at Science City?
What is the maximum annual turnover limit for Micro Enterprises as per the classification guidelines for manufacturing and service enterprises?