Question
A work is done by A, B, C and D together. The percentage of work done by A, B C and D are in arithmetic progression (A
- I : Numerical value of X is the perfect cube (I
- I : X (II
- I : X is the product of the 1000 and the square of 3
- P . The first, second, third and fourth term in the AP is the percentage of work done by A, B, C and D respectively. C works for nine days and complete (3/10)th the work and A and B worked for two days and three days only respectively and the remaining work is done by D. D alone can complete the total work in ‘m’ days and all four together can complete the whole work in four days. Total wages allotted for the work is Rs 45000 when they worked together to complete the work. The difference in the wages received by A and D is Rs. X. Find which of the statement is/are true. (
More Time and work Questions
- N workers can complete a piece of work in 50 days. When 5 more workers joined, then the work got completed in 40 days, then what is the value of N?
- A and B can complete a piece of work together in 6 days. A alone can complete it in 15 days. In how many days can B alone complete the work?
- Efficiency of A, and B are in the ratio of 3 : 4. If both can do a work together in 30 days. Find out how much days A will take to complete the work alone?
- Arjun and Bheem can do a piece of work in 8 and 10 days respectively. If they started the work together and worked on it for 3 days, then find the time tak...
- A, B and C can complete the whole work in 20 days. A starts the work and works for ‘x’ days while B and C complete the remaining 3/5 of the work in 15 days...
- Avinash is twice as good as Bhuvanesh and together they can finish a job in 50 days. Bhuvanesh will finish the work alone in how many days?
- 'A' and 'D' together can finish a project in 40 days. If 'D' alone can complete 25% of the project in 15 days, then find out how long it takes for 'A' alon...
- Efficiency of a man is 50% more than that of a woman. (n - 10) men working 6 hours a day can complete a task in 15 days, whereas (n - 9) women working 6 ho...
- ‘A’ can do a piece of work in 12 days. ‘B’ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.1540, then fin...
- Anurag can finish a task in 60 days, while Bhuvan can complete the same task in 80 days. Anurag begins working alone, and after 39 days, Bhuvan joins him. ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)