Question
X and Y can complete a work in 12 days and 10 days
respectively. With the help of Z, X and Y together can complete the work in 5 days for a total salary of Rs 6000. So how much should 2 get paid for his share of the work?Solution
- Work done by X in 1 day =1/12 Work done by Y in 1 day =1/10 1 Work done by (X+Y) in 1 day=1/12+ 1/10 =11/60 Β Work done by (X+Y) in 5 days =11/60) Γ5=11/12 Β Work left = 1-11/12=1/12 Hence, work done by Z in 5 days = 1/12 Β Hence, share of 2 in total salary 6000 = 6000x1/12 = 500.
Which figure should replace the question mark (?) if the following series were to be continued?
What should come in place of the question mark (?) in the given series based on the English alphabetical order?
WKG UHC SEY QBU OYQ ?
According to the equation P4Q5R5S, what is the relation between the son of P to son of S?
In a certain code language,Β NEST is written as 8426,Β WISE is written as 6912, andΒ RAIN is written as 7859.
The letters do not correspond to ...
What will come in the place of β?β in the following equation, if β+β and βββ are interchanged and βΓβ and βΓ·β are interchanged?<...
Which of the following numbers will replace the question mark (?) in the given series?
4, 11, 19, 31, 52, 89, ?
In the following question, select the odd group of numbers from the given alternatives.
10 is related to 15 following certain logic. Following the same logic, 42 is related to 63. To which of the following numbers is 22 related, following t...
In CABLES is coded as 720 and WEBINAR is coded as 819, then how will MANDOLIN be coded?
If β+β means βΓβ, βββ means βΓ·β, βΓβ means β+β, and βΓ·β means βββ, then what will be the value of the following ...