Question

    2 men and 3 boys can do a piece of work in 405 days while 3 men and 2 boys can do the same work in 324 days. In how many days can 5 men and 5 boys do that work?

    A 175 Correct Answer Incorrect Answer
    B 180 Correct Answer Incorrect Answer
    C 176 Correct Answer Incorrect Answer
    D 177 Correct Answer Incorrect Answer

    Solution

    According to the question, (2M+3B) x405 = (3M + 2B) ×324   810M+1215B=972M+648B 972M-810M=1215B-648B 162M = 567B M = 567B /162=7B / 2 Let 5 men and 2 boys complete the work in (x) days. (5M+5B) x = (3M + 2B) ×324 (5x7B/2+5B) x = (3x7B/2+2B) x324 (35B+10B) ×x/2=(25B×324)/2 (45B×x)/2 =25B×324)/2 X=(324×25B)/45B X=180days.

    Practice Next

    Relevant for Exams:

    ×
    ×