20 workers are employed to complete a work in 40 days.
But some workers leave the job after 16 days of work. The remaining workers complete the work in 46 days from its beginning. How many workers left the job after 16 days? type-sscSolution
D₁ = (40-16) = 24 D2=(46-40) =6 Let the M1=x and M2=x-4 M₁D₁ = M2 D2 X × 24 = (20-x) ×6 4x=20-x 5x=20 x=4 Hence, after 16 days 4 workers left work.
Which of the following type of aquifers is also known as 'Water Table Aquifer'?
Recently, Indian Oil rolled out brand new M15 Petrol which is a 15% blend of Methanol with Petrol in which state?
What is the purpose and potential impact of the "Saral" portal launched by the Union Government of India to improve the ease of living for the common man?
In Human Development Report 2021-22, which of the following country became the best performer in Indian-Subcontinent?
Minimum support price was applied on the recommendation of _____.
Which of the following is a tropical grassland?
Which Indian state is using drone technology and a digital platform to revive the PM-KUSUM programme?
The National Rural Livelihood Mission (NRLM) primarily focuses on which of the following?
The Teesta treaty has become a bone of contention between India and
In optics, the refractive index of a substance is described by the formula n = c/v, where c is: