Question

    type-ssc

    20 workers are employed to complete a work in 40 days.

    But some workers leave the job after 16 days of work. The remaining workers complete the work in 46 days from its beginning. How many workers left the job after 16 days?
    A 5 Correct Answer Incorrect Answer
    B 3 Correct Answer Incorrect Answer
    C 4 Correct Answer Incorrect Answer
    D 6 Correct Answer Incorrect Answer

    Solution

    D₁ = (40-16) = 24                     D2=(46-40) =6         Let the M1=x and M2=x-4 M₁D₁ = M2 D2 X × 24 = (20-x) ×6 4x=20-x 5x=20 x=4 Hence, after 16 days 4 workers left work.