P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 days ‘P’ left the work and the remaining work was completed by Q and R together. Find in how many days the remaining work will be completed?
P – 20 days P – 6 unit Q – 24 days LCM = 120 Q – 5 unit R – 30 days R – 4 unit Work of all 3 per day is (6 + 5 + 4) – 15 units All worked for 4 days. So, 4 days work is 4 × 15 = 60 units Remaining work = 120 – 60 = 60 units That work done by Q and R their per day unit = (5 + 4) = 9 unit Remaining work done by Q and R is 60/9 days = 6(2/3) days
I. p2 - 19p + 88 = 0
II. q2 - 48q + 576 = 0
I. 20x² - 93x + 108 = 0
II.72y² - 47y - 144 = 0
I. 2x2– 25x + 33 = 0
II. 3y2+ 40y + 48 = 0
I. 27x6- 152x3+ 125 = 0
II. 216y6- 91y3+ 8 = 0
I.√(3x-17)+ x=15
II. y+ 135/y=24
I. 8a2 – 22a+ 15 = 0
II. 12b2 - 47b + 40=0
In each of these questions, two equations (I) and (II) are given.You have to solve both the equations and give answer
I. x2 – ...
I. 27x6-152x3+125=0
II. 216y6 -91y3+8=0
I. x2 - 20x + 96 = 0
II. y2 - 23y + 22 = 0
I. y² - 7 y – 18 = 0
II. x² + 10 x + 16 = 0