Question
36 painters can paint a building in 45 days. If 18
painters started the work and after 30 days ‘v’ more painters joined them such that the remaining work got completed in 15 days, then find the value of ‘v’.Solution
Total work = 36 × 45 = 1620 units Work completed by 18 painters in 30 days = 18 × 30 = 540 units Remaining work = 1620 – 540 = 1080 units Let the number of painters added be ‘v’. Therefore, (18 + v) × 15 = 1080 270 + 15v = 1080 15v = 810 v = 54 Number of painters added = 54
What was the theme for World Day Against Child Labour observed on June 12, 2025?
Which initiative was launched by the Union Government to address the maritime trade deficit of $50 billion?
Which bank has entered into a partnership with Aditya Birla Sun Life Insurance to provide insurance solutions to its customers?
SEBI has come out with a “stricter timeline” for disclosure of material events or information by listed companies and introduced criteria for determ...
Who is roped as the brand ambassador of PharmEasy?
Who finished second in the SuperUnited Rapid and Blitz 2025 chess tournament?
According to the U . S . Trade Representative, what is one of the primary concerns leading to India's inclusion on the 'priority watch list'?
What historic milestone did the Indian para-athlete Deepthi Jeevanji achieve at the World Para Athletics Championships 2024?
Which phrase is the official motto of INS Nilgiri?
Which country had the largest investment share in Indian mutual funds during FY25?