Question
50 children can decorate a hall in 25 days. If 25
children began decorating and after 10 days βzβ additional children joined, completing the decoration in 20 more days, find βzβ.Solution
Total work = 50 Γ 25 = 1250 units Work completed by 25 children in 10 days = 25 Γ 10 = 250 units Remaining work to be completed by (25 + z) children = 1250 β 250 = 1000 units Therefore, (25 + z) Γ 20 = 1000 Or, 25 + z = 1000 / 20 Or, 25 + z = 50 Or, z = 50 β 25 = 25 Number of children added = 25
A can complete a task in 20 days, and B can complete it in 25 days. When B and C collaborate, they can finish the same task in 75/8 days. Now, if A and ...
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
- If Arjun can complete his work in 28 days by working 4 hours a day, how many hours a day should he work to finish the same work in 16 days?
Ajay started a work and left working after 8 days. Vijay finished the remaining work in next 36 days. Had Ajay left the work after working for 12 days t...
'Amit' can finish a __ percentage of work in 4 days on his own. 'Bishnu' requires 4 days less than 'Amit' to complete the same task individually. Conseq...
"Bhanu" is 37.5% more productive than "Anurag," the two of them can finish the entire task in 40 days. Determine how long it took "Anurag" by himself to...
Ashish and Anil can do a piece of work in 12 days and 15 days respectively. Ashish completed 30% of the work. Find the time taken by Anil to complete th...
- A team of workers can finish a task in 36 days. However, 5 workers leave the task every day, and it gets done in 48 days. Find the time needed for 90 worke...
Rahul, Sameer, and Dinesh can complete a task in 24 days, 36 days, and 18 days, respectively. They started working together, but ...
A and B together can complete a piece of work in 35 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12....