Total work = LCM of 50, 100, and 150 = 300 units. Mohan's daily work = 300/50 = 6 units. Sohan's daily work = 300/100 = 3 units. Rohan's daily work = 300/150 = 2 units. Work done in the first 8 days = 8 × (6 + 3 + 2) = 88 units. Work done by Sohan and Rohan together in the next 14 days = 14 × (3 + 2) = 70 units. Remaining work = 300 - 88 - 70 = 142 units. Time taken by Rohan to complete the remaining work = 142/2 = 71 days. Total days Rohan worked = 8 + 14 + 71 = 93 days.