Start learning 50% faster. Sign in now
ATQ, Number of days taken by Amit to finish the target= (6/25) × 10 = 24 days Number of days taken by a Geeta to finish the target = (6/40) × 100 = 15 days Let the total target be 120 units. (LCM of 24 and 15) Efficiency of Amit = (120/24) = 5 units/day Efficiency of a Geeta = (120/15) = 8 units/day Required number of days = {120 × (15/100) } ÷ (5 + 8) = (18/13) days
Select an appropriate figure from the four options that will come in the place of question mark (?) and complete the figure.
Which figure should replace the question mark (?) if the series were to continue?
In each of the following questions, find out which of the answer figures can be formed from the pieces given in the problem figure.
Select an appropriate figure from the four options that would complete the figure.