Question
A can complete a piece of work in 27 days. He worked for
21 days and then B finished the remaining work in 8 days. In how many days can A and B finish the work together?Solution
A can complete a piece of work in 27 days. A does the work in 27 days =1 A does the work in 1 day =1/27 A does the work in 21 days = (1/27) ×21=7/9 Remaining work =1-7/9 =2/9 Remaining work finished by B in 8 days =8×9/2=36days. A and B together finish the work – 27               36          108 4                 3 =108/4+3 =108/7  =15(3/7) days.
Which of the following is the primary function of a "VPN" in a computer network?
The actual data stored in a database at a particular moment in time is called:
 POST stands for ...........
Which memory type provides the largest storage capacity?
Which input device is used to capture images and videos?
Which of the following is the least secure method of authentication?
What is the use of SUM formula in Excel?
In cloud computing, SaaS stands for:
LAN stands for :
Why is it recommended to create strong and unique passwords?