ATQ, Time taken by 'G' to complete the whole job alone = 24×( 4/3)=32 days Let the total amount of work = LCM of 32 and 16 = 96 units Efficiency of 'G' =96/32 = 3 units per day Efficiency of (G + H) = 96/16= 6 units per day Efficiency of 'H' = 6−3 = 3 units per day Desired time = (0.25 × 96/3) = 8 days
Which answer figure will complete the pattern in the question figure?
In each of the following questions which one of the answer figures shall complete the given question figure.
In each of the following questions, select a figure from amongst the four alternatives, which when placed in the blank space of figure (X) would complet...
In each of the following questions, select a figure from amongst the four alternatives, which when placed in the blank space of figure (X) would comple...
In each of the following questions, select a figure from amongst the four alternatives, which when placed in the blank space of figure (X) would comple...
Select the number-pair in which the numbers are similarly related as in the given pair.
345: 144
Identify the figure that completes the pattern.
In each of the following questions which one of the answer figures shall complete the given question figure.
Which answer figure will complete the pattern in the question figure?
Identify the missing figure from the answer figures to complete the matrix given below.