'Sumit' can complete (3/8) of a job in 24 days, where as
'Sumit' and 'Tarun' together can finish it in 16 days. Calculate the time 'Tarun' needs to complete 60% of the job alone.Solution
ATQ, Time taken by 'Sumit' to complete the whole job alone = 24×( 8/3) = 64 days Let the total amount of work = LCM of 64 and 16 = 64 units Efficiency of 'Sumit' =64/64 = 1 units per day Efficiency of (Sumit + Tarun) = 64/16 = 4 units per day Efficiency of 'Tarun' = 4 − 1 = 3 units per day Desired time = (0.60 × 64/3) = 12.8 days
What does a Venturimeter measure in an irrigation pipeline?
What was the main objective of the Firka Development Scheme initiated in Madras Presidency in 1946?
The anal lobe of mosquitoes is capable of absorbing which of the following substances or materials?
Among common insect monitoring tools, which of the following would be considered an unbiased sampling strategy for population estimates?
The department of agriculture, revenue and commerce was set up in .............................?
Which is the lead agency for implementing e-NAM?
Growth stunting and pale yellow colour of the leaf is caused due the deficiency of which nutrient?
The Beaufort scale is for describingÂ
A major biochemical change during ripening of climacteric fruits is:
Which of the following sequence regarding dominant trait in pea plant is incorrect?