Question
βAβ can complete a work in 20 days and is 20% more
efficient than βBβ. βAβ and βBβ start the work together, but βAβ leaves after 10 days. The remaining work is completed by βBβ alone in βxβ days. Find the value of βxβ.Solution
ATQ, Time taken by βBβ to complete the work = 1.2 Γ 20 = 24 days Let the total work = 120 units Efficiency of βAβ = 120/20 = 6 units/day Efficiency of βBβ = 120/24 = 5 units/day Work completed by βAβ and βBβ in 10 days = (6 + 5) Γ 10 = 110 units Therefore, x = (120 β 110)/5 = 2 days
The 'Dandi March' was associated with which movement?
The "History of British India" is a three-volume work by ________.
Curzon Wyllie, assassinated by Madan Lal Dhingra in London, held which position?
The Indian Home Rule Society was established in which year?
In which year did the Kohat riots occur in the North-West Frontier Province?
Who built the Tower of Victory (Vijay Stambha) in the Chittor Fort?
With reference to Permanent settlement system of land Revenue policy of British, consider the following statements:
1. Hereditary rights of Zamin...
In which year did Raja Ram Mohan Roy start the publication 'Mirat-ul-Akhbar'?
The Danes formed an East India company and established their headquarters at?Β
Who initiated the first school for Muslim girls in British India?