Question
'x' men can complete a work in 60 days. If there had
been 20 more men, the work would have been completed in 30 days. Find the value of 'x'.Solution
According to the question, the total amount of work is 60x units. Therefore: 60x=(x+20)×30 60x=30x+600 30x=600 x = 600/30 x = 20
- Agricultural Census is conducted by Ministry Of Agriculture every ______years with the participation of states and UTs since 1970 as a part of World Agr... 
- Which of the following is not a sedimentary rock? 
- Wheat, Barley, Gram and Mustards are an example of 
- Apiculture deals with rearing of? 
- Which one is correct for Pradhan Mantri Kisan Maan Dhan Yojana (PM-KMY) 
- Which of the following is also called Golden Fiber? 
- Rural Infrastructure Development Fund (RIDF) is under 
- Ozone layer which absorbs and scatters the solar ultraviolet radiation is present in which layer of atmosphere? 
- Yellow revolution is related to which of the following? 
- Who has been designated as the "Youth Voter Awareness Ambassador" for Jammu & Kashmir by the Election Commission of India?