A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
Apatite is a group of minerals which mainly contains___
Out of the given options, which amino acid is classified as an essential amino acid, meaning it cannot be synthesized by the human body and must be obt...
The National Policy for Farmers, 2007 was formed on recommendations of National Commission on Farmers, 2006 under the chairmanship of __________
How much area should be covered by Forest according to forest policy 1988?
Which crop is commonly referred to as the "Camel Crop" due to its remarkable ability to endure prolonged drought conditions?
Gram staining is an example of ________.
Which are of the following describes the characteristics of Sedges?
The Modi administration has allocated Rs 450 crore for which among the following?
One-step resource for managing all activities of food testing through online interface is called as:
The most economical means of managing the ‘tungro virus’ disease in rice is: